Project Planning and Control Part 7
Thông tin tài liệu:
Nội dung trích xuất từ tài liệu:
Project Planning and Control Part 7 28 Worked examples The previous chapters describe the various meth- ods and techniques developed to produce mean- ingful and practical network programmes. In this chapter most of these techniques are combined in two fully worked examples. One is mainly of a civil engineering and building nature and the other is concerned with mechanical erection – both are practical and could be applied to real situations. The first example covers the planning, man- hour control and cost control of a construction project of a bungalow. Before any planning work is started, it is advantageous to write down the salient parameters of the design and construction, or what is grandly called the ‘design and construction philosophy’. This ensures that everyone who participates in the project knows not only what has to be done but why it is being done in a particular way. Indeed, if the design and construction philosophy is circulated before the programme, time- and cost-saving suggestions may well be volunteered by some recipients which, if acceptable, can be incorporated into the final plan. Worked examples Example 1 Small bungalow Design and construction philosophy 1 The bungalow is constructed on strip footings. 2 External walls are in two skins of brick with a cavity. Internal partitions are in plasterboard on timber studding. 3 The floor is suspended on brick piers over an oversite concrete slab. Floorboards are T & G pine. 4 The roof is tiled on timber-trussed rafters with external gutters. 5 Internal finish is plaster on brick finished with emulsion paint. 6 Construction is by direct labour specially hired for the purpose. This includes specialist trades such as electrics and plumbing. 7 The work is financed by a bank loan, which is paid four-weekly on the basis of a regular site measure. 8 Labour is paid weekly. Suppliers and plant hire are paid 4 weeks after delivery. Materials and plant must be ordered 2 weeks before site requirement. 9 The average labour rate is £5 per hour or £250 per week for a 50-hour working week. This covers labourers and tradesmen. Figure 28.1 Bungalow (six rooms) 257 Project Planning and Control 10 The cross-section of the bungalow is shown in Figure 28.1 and the sequence of activities is set out in Table 28.1, which shows the dependencies of each activity. All durations are in weeks. The activity letters refer to the activities shown on the cross-section diagram of Figure 28.1, and on subsequent tables only these activity letters will be used. The total float column can, of course, only be completed when the network shown in Figure 28.2 has been analysed (see Table 28.1). Table 28.1 Activity Activity – description Duration Dependency Total letter (weeks) float A Clear ground 2 Start 0 B Lay foundations 3 A 0 C Build dwarf walls 2 B 0 D Oversite concrete 1 B 1 E Floor joists 2 C and D 0 F Main walls 5 E 0 G Door and window frames 3 E 2 H Ceiling joists 2 F and G 4 J Roof timbers 6 F and G 0 K Tiles 2 H and J 1 L Floorboards 3 H and J 0 M Ceiling boards 2 K and L 0 N Skirtings 1 K and L 1 P Glazing 2 M and N 0 Q Plastering 2 P 2 R Electrics 3 P 1 S Plumbing and heating 4 P 0 T Painting 3 Q, R and S 0 0 = Critical Table 28.2 shows the complete analysis of the network including TLe (latest time end event), TEe (earliest time and event), TEb (earliest time beginning event), total float and free float. It will be noted that none of the activities have free float. As mentioned in Chapter ??, free float is often confined to the dummy activities, which have been omitted from the table. 258 0 2 5 7 9 14 A B C E F 1 2 3 5 7 9 2 3 2 2 5 0 2 5 7 9 14 5 6 9 12 14 D G 4 6 8 10 1 3 6 7 11 14 14 16 22 25 2 ...
Tìm kiếm theo từ khóa liên quan:
Project Management lập kế hoạch dự án hướng dẫn quản lý dự án phương pháp lập dự án tài liệu quản lý dự ánGợi ý tài liệu liên quan:
-
35 trang 231 0 0
-
Lecture Introduction to software engineering - Week 3: Project management
68 trang 186 0 0 -
Giáo trình Quản lý dự án phần mềm
243 trang 127 0 0 -
Ebook The procurement and supply manager's desk reference: Part 1
264 trang 122 0 0 -
Ebook Managing projects in human resources, training and development – Part 1
105 trang 122 0 0 -
Project management – Achieving competitive advantage
562 trang 95 0 0 -
106 trang 92 0 0
-
Bài giảng Quản lý dự án: Giới thiệu môn học - TS. Nguyễn Thúy Quỳnh Loan
19 trang 72 0 0 -
Bài giảng Quản lý dự án phần mềm: Quản lý tổng thể - Nguyễn Anh Hào
30 trang 58 0 0 -
fundamentals of project management (4th edition): part 1
111 trang 56 0 0 -
274 trang 55 0 0
-
Phân tích SWOT và giải pháp cho thị trường Bảo hiểm Việt Nam
4 trang 55 1 0 -
128 trang 53 0 0
-
project management (5th edition): part 1
392 trang 53 0 0 -
118 trang 51 0 0
-
Ebook Effective project management: Traditional, agile, extreme (5th ed): Part 1
549 trang 49 0 0 -
Bài giảng Quản trị dự án - Chương 4
16 trang 49 0 0 -
Ebook Operations management (7/E): Part 2
495 trang 48 0 0 -
11 trang 46 0 0
-
Ebook Construction management for industrial projects: Part 1
206 trang 43 0 0